- Cement Concrete Paver Blocks Flooring:
- Providing and laying factory made coloured chamfered edge Cement Concrete paver blocks of required strength, thickness & size/shape, laid in required colour & pattern over 50mm thick compacted bed of fine sand, compacting and proper embedding/laying of inter locking paver blocks into the Grid Powder (buzza), filling the joints with Grid Powder (buzza) and cutting of paver blocks as per required size and pattern, finishing and sweeping extra Grid Powder (buzza) in footpath, parks, lawns, drive ways or light traffic parking etc.
- PROCEDURE OF STAMPED CONCRETE
- Removal of old flooring tiles and disposal of removed debris.
- The second step is to clean and wash the entire surface properly.
- Where PCC is damaged and broken, proper rubble soling will be done with 100 mm thick PCC.
- Black plastic paper will be spread over the entire surface so that the water quality of the stamped concrete will not be absorbed into the ground.
- 8 mm steel will be used over the entire surface (Wherever required only) and its spacing will be maintained at 150mm.
- After that shuttering as per surface levelling and spread 150mm concrete properly.
- After spreading the concrete, 3 coats of hardener of 10 to 12 mm thickness will be applied with the help of Hand Trowel machine.
- After applying the release coat on the entire surface, the selected design rubber stamp is properly pressed and designed.
- Curing should be done for 7 days after the complete work of concrete.
- After that, grove cutting at a distance of 3mtr x3mtr on the entire surface and washing.
- Apply 1st and 2nd coat sealer after complete surface jet washing and proper drying.
- Cleaning and finish the work.
- TRIMIX CONCRETE WORK:
- Providing & laying LDP 200 micron on base floor.
- laying & spreading concrete with site-mixer, floors well compacted, mechanically vibrated dewatered by vacuum process "TRIMIX" floated with trowelled to get desired smooth finishing to required levels, over a levelling course, including M.S. shuttering, curing etc. Complete. The suitable width of panel should be 3mtr to 3.5mtr. The contraction/ sawed joints to be formed at every 3mtr to 3.5mtr distance by grooving with mechanical saw. The width of 4mm and depth of the groove sawed joint should be 18mm, and operation should be carried out as soon as concrete is ready to accept the saw cut without trowelling. The joint should be filled with bitumen. The construction joint is formed by square edge.
- Providing and Sprinkle of Non-Colour Floor Hardener @4kg/ Sq.Ft. (non-colour dry shake) shall be sprinkled over green concrete 1/3rd of the dry shake shall be broad-casted in first pass same is floated with power floater, remaining 2/3rd of dry shake is sprinkled in next pass thus the floor laid is floated and trowelled to acquire smooth finish.